Rural Hub
Back

5 key points for landowners and farmers facing utility works

5 mins

Hundreds of miles of new and upgraded infrastructure is needed for the Government to meet its targets for levelling up and for the UK to be net zero by 2050.

New housing, commercial development, and the move to renewable energy technologies like solar, battery and vehicle charging points, is increasing the pressure for a new and upgraded utility and travel infrastructure.

National Grid estimates that over five times the amount of new electricity transmission infrastructure will need to be delivered in the next seven years than has been built in the past 30 years.

Landowners and farmers are likely to be affected by these works given the number of cables and pipelines crossing farmland and the countryside.

Here are 5 key points to consider when approached by a third party looking to carry out such works:

1. Take professional advice early

Utility and infrastructure providers pay reasonable professional fees so landowners should have no hesitation in appointing a land agent. Whether the provider wants to carry out maintenance on an existing electricity, water, sewer or gas pipeline, or more complex works such as installing a new electricity supply, pipeline or the construction of a road or rail track, professional advice is imperative.

Even routine maintenance or small repairs do not always run smoothly, frequently causing far greater levels of disturbance and inconvenience than initially anticipated. 

Strutt & Parker is highly experienced in this work, making sure those affected receive the full advice and compensation package which they are entitled to. By taking advice early there may also be more opportunities to influence the design stage and reduce short- and long-term impacts on your property.

2. Know the specific rights and responsibilities of the third party

Most infrastructure projects follow a similar process but the statutory powers and rights available to third parties who carry out these works are very different. Survey works initially help determine whether the permanent works can take place. Preliminary works may be exercised such as hedgerow removal, boreholes or archaeology digs. A notice may be served, but sometimes landowner/occupier consents may be necessary, or a licence required.

Procedures can be different for temporary compounds and storage areas.  Permanent works, like a new water pipeline, can be carried out by notice, but works such as the construction of a substation or reservoir may require a land purchase.

Third parties usually prefer to enter land or purchase it by agreement. The water industry in particular has very comprehensive rights of access compared to other providers who are more reliant upon consent. A hybrid scenario can be adopted depending on the works, but we can advise and make sure the correct procedures are followed.

3. Consider steps to mitigate both short- and long-term impacts

This is really important and will depend on when the works commence. Third parties will try to work around farming activities where this will reduce crop loss and surface damage claims but this is not always possible. Other losses requiring careful consideration are Basic Payment Scheme and Stewardship payments which may need to be repaid or penalties may arise from the works. Implications could extend to a Lump Sum Exit Scheme application and delinked payments where the works have taken place during the relevant reference periods. Where the works take longer or are delayed there can be additional impacts, so communication is key.

Accommodation works such as installing new fencing, alternative access provisions, water troughs and drainage should be discussed so these are clearly understood before works commence.

Longer term impacts include safeguarding the land for future development or other land use opportunities such as renewable energy, Biodiversity Net Gain or tree planting. In certain cases, it may be necessary to understand what rights are available to request for the infrastructure to be relocated in the future or to negotiate a lift and shift provision.

4. Keep accurate records and a diary

This is essential. Most infrastructure projects last many months and even years during which time personnel can change. A pre-entry photographic record of condition of the land should be made no matter the scale of the works. The availability of drones in particular means it is now easier to do this which provides invaluable evidence when negotiating a claim later down the line. The onus to prove loss is on the claimant, so we strongly advise the landowner/occupier to take photographs and keep records of activities at all stages.

Lost time is a legitimate head of claim category when looking at the compensation due. A claimant should keep an accurate diary of their time spent in meetings, telephone calls and emails with their adviser, the third party or their contractors. The movement of livestock to accommodate the works and additional travelling time when harvesting crops are also legitimate claims. We find that those who retain invoices, quotes and time records are in a much stronger negotiating position, with settlements often reached more quickly.

5. Understanding the procedures for compensation claims and reinstatement

Compensation aims to ensure the claimant is no worse off – so far as money can achieve this. Depending on the nature of the interests being acquired claims can involve land purchases, agreeing easements, wayleaves, or other arrangements. Interim claims may be appropriate.

There are standard heads of claim, but additional compensation is payable in certain cases. Settlements tend to be reached by negotiation, but legislation provides a fall-back mechanism.

Land reinstatement can be problematic depending on the damage caused, contractor availability and weather conditions. Once handed back, temporary fencing may remain in place to aid land recovery. It is important to know timings and responsibilities, with agreements for doing the work agreed in advance. There may be future maintenance liabilities for accommodation works to decide and damage, like drainage, may not be immediately apparent but should not be overlooked.

With subtle differences in the statutory rights available to utility providers, it is important professional advice is taken as soon as approached to ensure that your position is not prejudiced unnecessarily.

Claims can be complex and take time to resolve, so seek assistance and do not miss out on compensation that you are entitled to.

Strutt & Parker prepares claims for both landowners and occupiers, so if you would like to speak to a member of the team about such matters please contact Matthew Cornish.

Matthew Cornish
Associate Director
Harrogate
+44 1423 706761
Send a message to Matthew Cornish
5 mins

Related Articles

06.06.2023

Unleashing Rural Opportunity: What’s been promised?

The Government’s charm offensive to win over the countryside continues. Just weeks after it held the Farm to Fork Summit at 10 Downing Street, the Government has unveiled a new rural action plan to deliver housing and jobs, alongside better digital connectivity and transport links, in the countryside. Defra Secretary of State Thérèse Coffey has […]
01.06.2023

Defra chooses evolution, not revolution on tenancy reform

The government has published its response to the independent Rock Review which in October 2022 put forward a set of 74 recommendations on measures to support the agricultural tenanted sector. After reviewing the recommendations, the government has announced it will be implementing the following main measures: Plans for a new Farm Tenancy Forum to support the […]
24.05.2023

Defra and the climb towards Net Zero

What is the problem? The UK Government is falling behind on its net zero emissions reductions targets, most strikingly so in the UK agriculture and land use sector. The Word Wide Fund for Nature (WWF) has analysed the figures from the Government’s Carbon Budget Delivery Strategy, published alongside a swathe of documents on the re-branded […]
15.05.2023

Research on long-term agreements for landscape recovery

Strutt & Parker has been involved in a project which seeks to address some of the challenges around the use of long-term agreements for landscape recovery in productive agricultural areas. Researchers at the Countryside and Community Research Institute (CCRI), based at the University of Gloucestershire, have worked in collaboration with Strutt & Parker to explore […]

Talk to us

Want to talk to us about our rural specialisms? Send us a message and we will make sure it gets to the right person.

Please write your name
Please write a message

Sign up

Sign up to be notified when we launch new publications so you’re always ahead of the research.

Please write your name
Please write a correct email address
Send me updates about
Please tick a box